Swapping old fixtures for LEDs saves energy, and utilities will often pay for part of it. But a larger retrofit can also pull the space into the commercial energy code's lighting rules. MI Energy prepares the lighting power and controls documents and helps with rebate paperwork. Your licensed electrical contractor installs the fixtures and buys the electrical permit.
When a retrofit triggers the energy code
Under the 2021 Washington State Energy Code, alterations that add or replace 20 percent or more of the luminaires in a space enclosed by walls or ceiling-height partitions, 20 percent or more of parking garage luminaires, or 20 percent or more of the installed exterior lighting wattage must meet the code's interior and exterior lighting requirements. Replacing only bulbs or ballasts, without raising the installed lighting power, is treated as a repair.
That means lighting power limits and lighting controls come into play. We show both on the permit documents.
Utility incentives
PSE Business Lighting: $0.30 per kWh of first-year savings for new LED fixtures and $0.60 per kWh with automatic controls, capped at 70% of project cost. PSE must approve the project and execute the grant before work starts; it says processing takes about 4 to 6 weeks. Tenant improvement projects use the Washington State Energy Code lighting power allowance as the savings baseline. Checked Nov 2026.
Tacoma Power Bright Rebates: $0.19 per kWh saved, up to 100% of eligible costs for small business lighting, and $0.17 per kWh, up to 60%, for general business lighting. Approval is required before the project starts. Checked Nov 2026.
What we prepare
• Existing and proposed fixture counts by space
• Lighting power calculations against the code allowance
• Lighting controls plan
• Energy code compliance forms for the building department
• Savings figures and documents for the rebate application
LED retrofit FAQ
Q: We're only replacing lamps. Does the code apply?
A: Replacing only bulbs or ballasts, without increasing installed lighting power, is treated as a repair under the code's exception.
Q: Should we apply for the rebate before ordering fixtures?
A: Yes. Both PSE and Tacoma Power require approval before work starts.
Q: Do you install the fixtures?
A: We prepare the design and documents. Your licensed electrical contractor installs them.